Our 711 House
http://www.renotalk.com/forum/topic/35160-our-711-house/page-2
Posted 14 February 2011 - 12:10 AM
Day 1 - 20th December: Hacking Day 1
Day 4 - 23rd December: Loading debris to truck.
Day 5 - 24th December: Loaded materials (cement, sand, tiles)
Day 8 - 27th December: Filling up the walls with cement before tiling
Day 10 - 29th December: Completed filling up of 2 toilets, kitchen and balcony walls.
Day 12 - 31st December: Tiled Kitchen (half) and Common Toilet
Day 17 - 5th January: Completed Tiling for Kitchen, Common Toilet, MBR Toilet. Started Living Room tilings
Day 18 - 6th January: Completed Rooms and almost there for living room. Felt the lines for our tiles are beautifully matched.
Day 21 - 9th January: Completed cement walkway @ entrance
Day 32 - 18th January: Completed aircon (with huge trunking!) , started electrical points
Day 33 - 19th January: Continued electrical points and more sockets!
Day 36 - 22nd January: Completed false ceilings. Where to get the lights?!
Day 41 - 27th January: Completed painting. Setting up parquet platform before closes for CNY
Day 44 - 30th January: Completed platform. Polish after CNY
Day 57 - 12th Feb: Completed lightings. Platform has been polished first round. Left glass door and kitchen cabinets!
Day 4 - 23rd December: Loading debris to truck.
Day 5 - 24th December: Loaded materials (cement, sand, tiles)
Day 8 - 27th December: Filling up the walls with cement before tiling
Day 10 - 29th December: Completed filling up of 2 toilets, kitchen and balcony walls.
Day 12 - 31st December: Tiled Kitchen (half) and Common Toilet
Day 17 - 5th January: Completed Tiling for Kitchen, Common Toilet, MBR Toilet. Started Living Room tilings
Day 18 - 6th January: Completed Rooms and almost there for living room. Felt the lines for our tiles are beautifully matched.
Day 21 - 9th January: Completed cement walkway @ entrance
Day 32 - 18th January: Completed aircon (with huge trunking!) , started electrical points
Day 33 - 19th January: Continued electrical points and more sockets!
Day 36 - 22nd January: Completed false ceilings. Where to get the lights?!
Day 41 - 27th January: Completed painting. Setting up parquet platform before closes for CNY
Day 44 - 30th January: Completed platform. Polish after CNY
Day 57 - 12th Feb: Completed lightings. Platform has been polished first round. Left glass door and kitchen cabinets!
all from lighting.com.sg? .. the price seems right
except the downlights, all are =)